January

The technical assignment drawn up, the evaporator was manufactured and supplied for power unit №3 of Tianwan NPP-2.
Construction, installation and setting-up were carried out during replacement of the elevators in power unit №2 of Balakovo NPP.
The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Construction and installation including installation of the elevators in the special sanitation block USP were carried out for the state needs under the project “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.
Construction and installation, including installation of the elevators in the power distribution block UBA, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

February

The technical assignment drawn up, evaporator, finishing evaporator, finishing intercooler for the primary circuit blowing were produced and sup-plied for power unit №3 of Tianwan NPP-2.
The technical assignment drawn up, evaporator, finishing evaporator, finishing intercooler for the primary circuit blowing were produced and sup-plied for power unit №3 of Tianwan NPP-2.

March

Construction, installation and setting-up were carried out during replacement of the elevators in power unit №2 of Balakovo NPP.
Metal working machinery was produced and supplied for power unit №4 of Beloyarsk NPP
Construction and installation including installation of elevators in the special sanitation block USP were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

April

The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Construction, installation and setting-up were carried out during replacement of the elevators in power unit №2 of Balakovo NPP.
A set of temperature controllers was manufac-tured and supplied for power unit №1 of Novo-voronezh NPP-2.
The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Cable laying and conduit installation were carried out in the utility tunnel from the OVK block to ALBK, KPP blocks and to BNS station at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

May

A set of temperature controllers was manufac-tured and supplied for power unit №1 of Novo-voronezh NPP-2.
Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

June

Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

July

The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Personal gamma/neutron self-reading dosimeters, personal gamma/beta self-reading dosimeters, a part of the automated system for radiation monitoring, were manufactured and supplied for power unit №1.
Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.
The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Control units of nuclear plant personnel contamination, a part of the Automated system for radiation monitoring, were manufactured and supplied for power unit №1 of Novovoronezh NPP-2.

Augustus

Detection assemblies, a part of the Automated system for radiation monitoring, were made and supplied for power unit №1 of Novovoronezh NPP-2.
Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.
The shut-off valves were made and supplied for power unit №1 of Novovoronezh NPP-2.
Liquid scintillation alpha/beta spectrometric radiometers, a part of the Automated system for radiation monitoring, were produced and supplied for power unit №1 of Novovoronezh NPP-2.
Setting-up and testing of elevator electrical equipment at no-load took place in ALBK (administrative and laboratory block) block of power unit №4 of Beloyarsk NPP.

September

Beta-ray spectrometer system, a part of the Automated system for radiation monitoring, was made and supplied for power unit №1 of Novovoronezh NPP-2.
Construction, installation and setting-up were carried out during replacement of the elevators in power unit №2 of Balakovo NPP.
Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

October

Construction, installation and setting-up were carried out during replacement of the elevators in power unit №2 of Balakovo NPP.
Detection assemblies, dosimeters, personal digital dosimeter, all are a part of the Automated system for radiation monitoring, were fabricated and supplied for power unit №1 of Novovoronezh NPP-2.
Construction and installation, including installation of elevators and duct banks in the special block 1UKS, were carried out for the state needs at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.
Setting-up and testing of elevator electrical equipment at no-load took place in ALBK (ad-ministrative and laboratory block) block of pow-er unit №4 of Beloyarsk NPP.
Cable laying and conduit installation were car-ried out in the utility tunnel from the OVK block to ALBK, KPP blocks and to BNS station at the construction site “The expansion of Beloyarsk NPP with power unit №4 and BN-800 reactor”.

November

Mobile radiometric units, dosimeters - radiometers, all are a part of the Automated system for radiation monitoring, were produced and supplied for power unit №1 of Novovoronezh NPP-2.
Contamination control units, a part of the Automated system for radiation monitoring, were manufactured and supplied for power unit №1 of Novovoronezh NPP-2.
Radiometric units, radiometer, detection assem-blies, all are a part of the Automated system for radiation monitoring, were produced and sup-plied for power unit №1 of Novovoronezh NPP-2.
Counting rate-meters, luminescent gamma-ray dosimetry system, all are a part of the Automated system for radiation monitoring, were produced and supplied for power unit №1 of Novovoronezh NPP-2.
Setting-up and testing of elevator electrical equipment at no-load took place in ALBK (administrative and laboratory block) block of power unit №4 of Beloyarsk NPP.
A portable spectrometer, filter holders, control unit of nuclear plant personnel contamination, which is a part of the Automated system for radiation monitoring, were manufactured and supplied for power unit №1 of Novovoronezh NPP-2.

December

Control units for volumetric activity of radioactive gases, a part of the Automated system for radiation monitoring, were manufactured and supplied for power unit №1 of Novovoronezh NPP-2.
Control units for volumetric activity of radioactive aerosols, radiometric units, all are a part of the Automated system for radiation monitoring, were produced and supplied for power unit №1 of Novovoronezh NPP-2.
Gamma-ray multichannel spectrometer for X-ray and gamma-ray detection, gamma-ray spectrometer, survey radiometer, all are a part of the Automated system for radiation monitoring, were produced and supplied for power unit №1 of Novovoronezh NPP-2.
Reader devices, a part of the Automated system for radiation monitoring, were developed, licensed, added to the Federal register MVI and MRK (Procedure of Measurements and Methods For Radiation Monitoring) finally produced and supplied to power unit №1 o
Automated spectrometer units for reactor coolant control and detection units for inert noble gases emissions were made and supplied.